When the HR Cement plant first started producing in August 2012, little did the team know how quickly their reputation, and so demand, would grow.
To satisfy this call from the market, our team has been building almost continuously since then, culminating in the second mill line being completed in 2022, and Eco-cem being produced
A rough time line of our expansion:
2012: Plant begins production with Mill, Bulk Silo 1, three QC Silos, and one Dispatch Silo
2013: Store 2 added
2014: Building roof apron joining the two stores complete
2015: Second Dispatch Silo erected
2016: 2000t Bulk Silo 2 completed
2017: Third clinker store added, third Dispatch Silo erected
2018: Weighbridge extended
2019: Pre-grinder added to production line to boost production, & new custom built process control system installed
2020: Mill 2 project begun
2021: New Offices completed, QC Silos 4 & 5 erected
2022: Mill 2 commissioned
This a remarkable history demonstrating our capacity and determination to continue to innovate in our industry.